BRP Gregorio Del Pilar Repairs Completed This Sept: PH Navy

6

BRP Gregorio Del Pilar Repairs Completed This Sept: PH Navy

6

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Repairs on the BRP Gregorio Del Pilar, which was damaged after a grounding incident in 2018, are expected to be completed this month, a Philippine Navy (PN) official said Tuesday night.

“The drydocking and other related repairs of BRP Gregorio Del Pilar (PS-15) are expected to be completed later in the month of September,” PN spokesperson, Commander Benjo Negranza, said in a message to the Philippine News Agency (PNA) when asked for updates on the ship.

One of the ship’s two variable pitch propellers was damaged, along with its propeller hub, after its grounding off Hasa-Hasa Shoal in August 2018.

“It will be undocked upon completion of the installation of underwater machinery, which is now ongoing. All other outstanding repairs will be done when PS-15 is back on the water,” Negranza added.

The PN earlier said difficulties in procuring parts and the ongoing coronavirus disease 2019 (Covid-19) pandemic have moved the completion of the repairs of the BRP Gregorio Del Pilar to the later part of 2021.

As this developed, the BRP Andres Bonifacio (PS-17), the sister ship of BRP Gregorio Del Pilar and BRP Ramon Alcaraz (PS-16), is now mission-ready after its maintenance and repair period.

“After more than a year of taking a break from operational demands in order to pay attention to its maintenance and repair requirements, BRP Andres Bonifacio (PS-17) is finally back and out at sea again,” a post on the ship’s Facebook page said Tuesday night.

In the same post, it was learned the BRP Andres Bonifacio completed its drydocking and other related repairs (DDORR) in Subic, Zambales on July 31 and the maintenance availability program from August 1 to 16.

“Relatedly, PS-17 successfully conducted its sea trial and 30-hour endurance run activities, which paved the way to upgrade its operational status to ‘mission-ready’ on 25 August 2021. The deliberate implementation of PS17’s DDORR program is vital to ensure the highest level of equipment reliability in order to sustain maximum operational readiness, safety, and ship survivability,” it added.

The BRP Andres Bonifacio received minor capability upgrades, such as the replenishment-at-sea capability, and the installation of a Mark 38 25-mm. gun system, new gun mounts, and additional tertiary guns.

These upgrades are in line with the Philippine Fleet’s to improve the ship’s readiness and capabilities.

“In no time, the ship will be once again patrolling our territorial waters, EEZ (exclusive economic zone), and other maritime areas of interest in support to the missions and objectives of the Offshore Combat Force, Philippine Fleet, Naval Operating Forces, and the PN in general,” it added.

The BRP Andres Bonifacio arrived in the Philippines on Dec. 9, 2016. (PNA)

Disclaimer: The views and opinions expressed on this website, including all written content, articles, and posts, are solely those of the individual authors, whether they are employees, contributors, or guest writers. These views and opinions do not necessarily reflect the official policy or position of the website's management, officers, partners, employees, affiliates, or any other associated entities. The content provided and the information contained therein are sourced independently by the respective writers and are not influenced, endorsed, or verified by the management or any other parties associated with the website. Readers are encouraged to conduct their own research and seek appropriate guidance before making any decisions based on the content of this site.